How to apply for a new KEDCO electricity connection

KEDCO's published connection route for a new premises, beginning with load assessment and an application prepared through a registered electrical contractor before KEDCO processes the supply request.

For applicants in Nigeria · Responsible organisation: Kano Electricity Distribution Company

VerifiedChecked 2026-10-05
WhatsAppShare text includes the current fee/status, last-checked date and this guide link. Watching saves a comparison snapshot on this device.

Steps for KEDCO new connection

01
Verify details

Open KEDCO's official FAQ and confirm the new premises' expected electrical load with a registered electrical contractor.

02
Continue

Have the registered contractor prepare the new-connection application and required technical information for KEDCO.

03
Verify details

Submit the application to KEDCO for load assessment and network-availability review.

04
Collect / finish

Receive KEDCO's technical decision on the connection arrangement, including whether a public or dedicated transformer is needed.

05
Payment

Pay only the official assessed connection charges and keep the approval/account details after KEDCO authorises the new supply.

Check before moving on

Confirm the applicant, service and amount on the responsible provider's payment screen before paying. Avoid unsolicited payment links.

Requirements for KEDCO new connection

1 Identity / account detail1 Other requirement2 Documents
01
Identity / account detail

The new premises address and intended electricity load requirement

02
Other requirement

A registered electrical contractor to prepare and forward the connection application under KEDCO's published route

03
Document

Technical information sufficient for KEDCO to assess whether the load can use a public transformer or needs a dedicated transformer

04
Document

Any customer identity/property information requested during KEDCO's connection assessment

Alternative application routes and troubleshooting
How to get this service

Choose the correct application route

Mostly online
Physical visit: evidence check

No mandatory physical visit is established by the documented steps

No compulsory walk-in step has been verified for the standard process. Ask the responsible agency if your case needs assistance.

If something blocks you

If this specific process gets stuck

Use KEDCO's official support/contact route. Supply a reference only if the service actually issued one.

View agency guidance →

Only authorised routes. We never present an unofficial agent, cybercafé or third-party payment page as an alternative unless the responsible agency authorises it.

My Process

Turn this guide into your personal checklist.

Track documents and steps on this device. No account is needed and your progress stays in this browser.

Important notes about KEDCO new connection

  • KEDCO's current FAQ says loads below 50 KVA can be connected through a public transformer when capacity is available, while higher loads need a dedicated transformer.
  • Actual connection voltage and infrastructure depend on load capacity and available mains.
  • A registered electrical contractor's involvement does not replace KEDCO's final technical approval.

Official KEDCO sources for KEDCO new connection

These cited sources support the details about KEDCO new connection. Last reviewed on 2026-10-05; check the responsible organisation's latest information before acting because prices, deadlines and processes may change.

Help keep this accurate

See something outdated?

Correction reporting is checked only when you choose to report an issue, keeping normal guide loads lighter.